Implementation Roadmap
90-Day Launch Plan & Quarterly Milestones
90-Day Launch Plan
Month 1: Foundation Setting (Days 1-30)
Current PhaseWeek 1-2: Internal Alignment
| Action | Deliverable | Owner | Status |
|---|---|---|---|
| Review strategy documents | Team alignment on priorities | Funder team | Done |
| Finalize portfolio budget | Approved ₹278-302 Cr allocation | Finance | Done |
| Establish PMU structure | Team roles, reporting lines | Leadership | In Progress |
| Set up communication channels | Slack/Teams, email lists | Operations | Pending |
Week 3-4: Partner Outreach
Tier 1 (Priority)
- NRDC India - Email + call Pending
- WRI India - Email + call Pending
- CEEW - Email + call Pending
- ITDP India - Email + call Pending
Tier 2
- Prayas, DA, Ethos, Final Mile - Introductory emails
- Saahas, TERI, CSTEP, Chintan - Introductory emails
Tier 3
- SFC, Vasudha, CSE, Saath - Schedule for Month 2
Milestone: 10 partner discovery calls completed by Day 30
Month 2: Partnership Development (Days 31-60)
UpcomingMOU Development
| Partner | MOU Elements | Target Signing |
|---|---|---|
| NRDC | Scale-up plan, Ethos integration, ASSURE linkage | Day 45 |
| WRI | PRADAN integration, equity framework | Day 50 |
| CEEW | Cooling + circular split, Saahas integration | Day 55 |
| ITDP | Transport demand focus, metrics | Day 55 |
| Development Alternatives | Rural buildings, Ethos linkage | Day 60 |
Integration Cluster Workshops
Buildings Cluster Workshop (Day 40)
Participants: NRDC, WRI, DA, Ethos, (IIHS ASSURE)
Agenda: Role clarity, handoffs, shared metrics
Circular Economy Cluster Workshop (Day 45)
Participants: CEEW, Saahas, TERI, CSTEP, Chintan, Saath
Agenda: Research-operations integration, policy timeline
Behavior & Awareness Cluster Workshop (Day 50)
Participants: Final Mile, CSE, Prayas
Agenda: Nudge design, campaign coordination
Milestone: 5 MOUs signed, 3 cluster designs complete by Day 60
Month 3: Operationalization (Days 61-90)
UpcomingDashboard MVP Launch
| Week | Deliverable |
|---|---|
| Week 9 | Data model finalized, Supabase setup |
| Week 10 | Partner data submission portal live |
| Week 11 | Executive summary dashboard draft |
| Week 12 | 5 Tier 1 partner dashboards live |
Launch Event (Day 85-90)
Format: Half-day portfolio convening
Participants: All 24 partner organizations
Agenda:
- Funder vision presentation
- Partner introductions (2 min each)
- Integration cluster breakouts
- Dashboard demonstration
- Year 1 priorities alignment
- Media announcement
Final Milestone: ₹50-60 Cr disbursed, dashboard MVP live, launch event completed
Year 1 Quarterly Milestones
Q1 (Months 1-3): Launch
- MOUs signed: 10/16
- First disbursements: ₹50-60 Cr
- Dashboard MVP: Live
- Launch event: Completed
- Baseline data: 80% metrics
Q2 (Months 4-6): Pilots
- MOUs signed: 16/16
- Pilot projects: 20+ launched
- Partner dashboards: All live
- Policy windows mapped: 10 state + 3 national
Q3 (Months 7-9): Scale
- Energy saved: 1.5 TWh
- Buildings optimized: 30,000
- Recycling capacity: 5,000 t/yr
- Policies influenced: 3
Q4 (Months 10-12): Results
- Energy saved: 2.0 TWh
- Buildings optimized: 50,000
- Recycling capacity: 8,000 t/yr
- Policies influenced: 5
Policy Window Calendar
| Policy | Window | Lead Partners | Action Required |
|---|---|---|---|
| Battery EPR Rules | Q2-Q3 2026 | Chintan, CEEW | Draft + advocacy by May 2026 |
| Solar Panel EPR | Q3-Q4 2026 | CEEW, Chintan | Build on battery success |
| ECBC Update | Q1-Q2 2027 | NRDC, SFC | State pilot evidence |
| National Cooling Action Plan | Ongoing | CEEW | State implementation |
| Green Building Mandate | State-specific | NRDC, WRI | State-by-state |
| Transport Demand Policy | City-specific | ITDP | BRT/TOD evidence |
| Architecture Education (CoA) | Q4 2027+ | Ethos | Evidence + advocacy |
Risk Monitoring & Escalation
Early Warning Indicators
| Risk | Indicator | Threshold |
|---|---|---|
| Partner underperformance | Quarterly milestone miss | 2 consecutive |
| Budget under-utilization | <70% quarterly | 2 consecutive |
| Integration failure | No cross-partner deliverable | 6 months |
| Policy window miss | Deadline approaching | 60 days out |
Escalation Protocol
Level 1
Partner: Single metric off track → Partner support call (Weekly)
Level 2
Cluster: Integration issue → Cluster lead intervention (Bi-weekly)
Level 3
Portfolio: Multiple partner issues → PMU review meeting (Monthly)
Level 4
Strategic: Systemic problem → Funder leadership decision (As needed)